Category 'Apartment'

13
Jun

The Mercantile – Construction Progress – June 2016

Apartment, Bothell, construction, framing, Multifamily, progress, The Mercantile | Comments Off on The Mercantile – Construction Progress – June 2016

Level 3’s PT slab was poured earlier this month, allowing the wood framing construction to begin. There is a 2 story elevation change from the west side of the property, off of 102nd Ave NE, to the east side of the property.  The topography meets the third floor on the east end of the building, […]

23
May

The Mercantile – Construction Progress – May 2016

Apartment, Bothell, construction, Multifamily, Residential, The Merc, The Mercantile | Comments Off on The Mercantile – Construction Progress – May 2016

The Level 3 post-tension slab is being laid out this week.  The back of the structure is beginning to emerge above ground.The supporting deck is assembled with some shoring along the edges.The concrete walls’ framework and shoring is occupying majority of floor space on site.  The image on the left displays where the new construction […]

18
Apr

The Mercantile – Construction Progress – April 2016

Apartment, Bothell, construction, Multifamily, progress, pt slab, slab on grade, The Mercantile | Comments Off on The Mercantile – Construction Progress – April 2016

The slab on grade is complete on the Mercantile site, located in Bothell.  The concrete columns are erected at the ground level.  Soon after, the level 2 deck was prepped for a concrete pour.The forms were constructed and lined with reinforced bars and ties, as illustrated in the image below.  The formwork for the concrete […]

22
Mar

The Mercantile – Construction Progress – March 2016

Apartment, Bothell, Breaking ground, construction, foundation, Multifamily, progress, Residential, The Merc, The Mercantile | Comments Off on The Mercantile – Construction Progress – March 2016

Over the past couple weeks the construction team has been pouring the remaining columns of the subgrade garage. The foundation and footings are complete and the second level PT slab will be poured in the next couple weeks.Keep updated with the Mercantile project by clicking here.

29
Feb

The Mercantile – Construction Progress – February 2016

Apartment, Bothell, Breaking ground, construction, Demo, Demolition, Multifamily, Residential, The Merc, The Mercantile | Comments Off on The Mercantile – Construction Progress – February 2016

The Mercantile is starting to take form.  The footings were completed and the columns are being erected at the lower levels.  The construction teams are proceeding to build the concrete garage walls and mapping the plumbing where pipes will puncture through concrete floor slabs and walls.We are excited to see the next steps for The […]

25
Jan

The Mercantile – Construction Progress – January 2016

Apartment, Bothell, construction, Demolition, excavation, foundation, grading, Multifamily, progress, The Mercantile | Comments Off on The Mercantile – Construction Progress – January 2016

The images illustrate the progress made over these past couple of weeks. The excavation process is complete on The Mercantile, a multifamily project located in Bothell. The construction teams have poured the footings and have erected the temporary shoring walls around the perimeter of the building. They are beginning to construct the subgrade garage walls.The […]

28
Dec

The Mercantile – Construction Progress – December 2015

Apartment, Bothell, construction, Demolition, grading, Multifamily, progress, The Mercantile | Comments Off on The Mercantile – Construction Progress – December 2015

The Mercantile located in Bothell, WA has completed demolition of the existing commercial building. The historic unreinforced masonry façade has been preserved along 102nd ave and the rest of the site has been cleared and graded.We are excited to see the next steps for The Mercantile, keep track of the construction progress by clicking here.

23
Nov

The Mercantile – Construction Progress – November 2015

Apartment, Bothell, Breaking ground, construction, Demo, Demolition, Multifamily, Residential, The Merc, The Mercantile | Comments Off on The Mercantile – Construction Progress – November 2015

The Mercantile will be a seven story multifamily apartment building.  The demolition phase has begun in the month of October.  The original building, the Cooperative Mercantile Company, is an unreinforced masonry structure.  The demolition team has been working to preserve the existing brick façade, which will be incorporated into the new design. The windows and […]

26
Oct

Capitol Hill Apartments – Construction Update – October

Apartment, Capitol Hill, construction, Construction Update, Grouparchitect, in progress, Multifamily, Seattle | Comments Off on Capitol Hill Apartments – Construction Update – October

The Capitol Hill Apartments construction team has completed the exterior framing.  Pedestrians are now able to visualize the upcoming structure.  The building’s penthouse level butterfly roof adds a recognizable angular skyline to the neighborhood.The structure is located atop a hill which allows for sweeping views out towards Lake Washington, the Cascade Mountains, and the local […]

18
Sep

The Mercantile – Breaking Ground

Apartment, Bothell, Breaking ground, construction, Multifamily, rendering, Residential, The Merc, The Mercantile | Comments Off on The Mercantile – Breaking Ground

We are excited to break ground and start construction on The Mercantile, a six story multifamily apartment building, located in the heart of downtown Bothell at the corner of 102nd & Main. The Mercantile will blend the old with new. Originally the site of the Cooperative Mercantile Company’s first building, ca 1908, the new structure will […]

4
Sep

Capitol Hill Apartments – Construction Update – September

Apartment, Capitol Hill, Construction Update, Grouparchitect, in progress, Seattle | Comments Off on Capitol Hill Apartments – Construction Update – September

The construction process for Capitol Hill is coming along, we are taking advantage of the sunny weather in Seattle.  The framing and sheathing was just completed on the third floor, and we had our first peak at the amazing views toward Lake Washington on the deck of level four.  The team will soon begin framing […]

15
Jul

Capitol Hill Construction-Update-July

Progress on our Capitol Hill Apartment is coming along. These past few weeks, the concrete level and PT deck have been placed and cured making way to start the framing process. Framing for Level 2 above the PT concrete deck is underway and it is awaiting the joist construction for the Level 3 floor deck.Window studs […]

16
Jun

LIV-Construction Update-June

Apartment, Bellevue, construction, Construction Update, Grouparchitect, in progress, Uncategorized | Comments Off on LIV-Construction Update-June

The LIV Apartments is almost ready to welcome new occupants this July!  The majority of the remaining project’s amenity spaces and landscaping have been completed, including the planters, pavement designs, roof decks, lounges, and many other features.The accent siding at the gateway entrance has been completed and landscaping is underway. The main walking path to […]

29
May

LIV Apartments – Aerial Photos – May

Aerial Photos, Apartment, construction, in progress, LIV Apartments, Project Update, Residential | Comments Off on LIV Apartments – Aerial Photos – May

The LIV Apartment is complete with the exterior framing and sheathing, the final exterior finishes will be applied during these next few weeks. We are excited and working hard to finish the West Building in preparation of new tenants in the month of July. The construction teams will continue to work on the remaining buildings.The outdoor […]

26
May

LIV Apartments – Construction Update Mid May 2015

Apartment, construction, in progress, LIV Apartments, Multi-family/Mixed Use, Project Update, Residential | Comments Off on LIV Apartments – Construction Update Mid May 2015

The West Building of the LIV Apartments is ready for occupants in July which is right around the corner. The construction team has been putting the final touches on the West Building’s units and amenity spaces. Construction will continue on the East, West, and South buildings. The vast majority of the exterior for the North, […]

24
Apr

LIV Apartment – Aerial Photos – April

Aerial Photos, Apartment, construction, in progress, LIV Apartments, Project Update, Residential | Comments Off on LIV Apartment – Aerial Photos – April

We have made a lot of progress at the LIV Apartment construction site. The exterior of the East Building is near completion. The East Building has the windows installed and is currently being wrapped with a weather protective membrane. The construction team will begin installing the concrete pavers and landscape to the roof decks, which […]

13
Mar

LIV Apartments – Aerial Photos – March

Aerial Photos, Apartment, construction, in progress, LIV Apartments, Multi-family, Project Update, Residential | Comments Off on LIV Apartments – Aerial Photos – March

Construction has been moving along during the month of March, the exterior framing of the East Building has been completed.  All the windows on the westerly buildings have been installed and the construction team is continuing to wrap the building with the weather protective membrane and continue installation of the building’s cladding systems.Due to the […]

7
Mar

LIV Apartments – Construction Update Mid March 2015

Apartment, construction, in progress, LIV Apartments, Multi-family/Mixed Use, Project Update, Residential | Comments Off on LIV Apartments – Construction Update Mid March 2015

The exterior shells of the North, South, East and West buildings were completed.  As you can see in the image above, the North Building’s building wrap is being applied against the sheathing.  It will soon look similar to the South Building, shown on the right, with the exterior finishes installed and painted. The corten steel […]

6
Feb

LIV Apartments – AERIAL PHOTOS – Feb.

Aerial Photos, Apartment, Construction, In Progress, LIV Apartments, Project Update, Residential, Uncategorized, update | Comments Off on LIV Apartments – AERIAL PHOTOS – Feb.

Construction at the LIV Apartments in Bellevue has made substantial progress in the recent month.  The East building has reached level 6 of framing and flooring including roof trusses.  The framing of the lower roof deck amenity space on the 5th level is complete and the green roof, concrete pavers, dog run, planters, and trees […]

20
Jan

LIV Apartments – Construction Update mid Jan 2015

Apartment, Construction, In Progress, in progress, LIV Apartments, Multi-family/Mixed Use, Project Update, Residential | Comments Off on LIV Apartments – Construction Update mid Jan 2015

On a recent office site visit to the ongoing LIV Apartments in Bellevue our team was able to observe all of the various stages of construction the project is currently in. This project utilizes phasing as strategy to minimize construction time by distributing the construction over multiple buildings so that the various trades can work […]