Capitol Hill Apartments – Construction Update – October

Apartment, Capitol Hill, construction, Construction Update, Grouparchitect, in progress, Multifamily, Seattle | Comments Off on Capitol Hill Apartments – Construction Update – October

The Capitol Hill Apartments construction team has completed the exterior framing.  Pedestrians are now able to visualize the upcoming structure.  The building’s penthouse level butterfly roof adds a recognizable angular skyline to the neighborhood.The structure is located atop a hill which allows for sweeping views out towards Lake Washington, the Cascade Mountains, and the local […]

4
Sep

Capitol Hill Apartments – Construction Update – September

Apartment, Capitol Hill, Construction Update, Grouparchitect, in progress, Seattle | Comments Off on Capitol Hill Apartments – Construction Update – September

The construction process for Capitol Hill is coming along, we are taking advantage of the sunny weather in Seattle.  The framing and sheathing was just completed on the third floor, and we had our first peak at the amazing views toward Lake Washington on the deck of level four.  The team will soon begin framing […]

15
Jul

Capitol Hill Construction-Update-July

Progress on our Capitol Hill Apartment is coming along. These past few weeks, the concrete level and PT deck have been placed and cured making way to start the framing process. Framing for Level 2 above the PT concrete deck is underway and it is awaiting the joist construction for the Level 3 floor deck.Window studs […]

26
Jun

LIV Apartments – Aerial Photos – June

Aerial Photos, Bellevue, Uncategorized | Comments Off on LIV Apartments – Aerial Photos – June

The LIV Apartments have applied the final exterior finishes including Hardi and cedar plank siding with metal panel and brick veneer siding as well. The rest of the roof gardens have been implemented and the main entrance has now been completed and tenants have moved into the building. The roof gardens contain, open community deck […]

20
Jan

LIV Apartments – Construction Update mid Jan 2015

Apartment, Construction, In Progress, in progress, LIV Apartments, Multi-family/Mixed Use, Project Update, Residential | Comments Off on LIV Apartments – Construction Update mid Jan 2015

On a recent office site visit to the ongoing LIV Apartments in Bellevue our team was able to observe all of the various stages of construction the project is currently in. This project utilizes phasing as strategy to minimize construction time by distributing the construction over multiple buildings so that the various trades can work […]

16
Jan

LIV Apartments – Aerial Photos – Jan.

Aerial Photos, Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – Jan.

January has been a productive month at the LIV Apartments in Bellevue.  Progress on the East Building has reached level 5 as framing crews continue to install wall panels and flooring.  Seen in the photo above, crews are framing a lowered roof deck amenity space that will soon be covered with green roof, concrete pavers, […]

6
Jan

LIV Apartments – Construction update January

Apartment, Construction, In Progress, LIV Apartments, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction update January

2015 arrives at the job site of the LIV Apartments in Bellevue as crews work at a fevered pace on both the exterior and interior of phase one, and on the framing of the phase 2 East Building. At breaks in the weather painting crews are able to paint the cement board panel siding that […]

2
Jan

Phinney Ridge Prefab – Module Set

Exciting news on the Pre-fab home front here at Grouparchitect!  The latest collaboration with Method homes is taking shape in the Phinney Ridge neighborhood of Seattle.  This Option series house has been in the works for the last few months, and as detailed in previous blog posts progress has been continuing steadily.  The most exciting part […]

22
Dec

LIV Apartments – Aerial Photos – Dec.

Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – Dec.

December has been a busy month at the LIV Apartments.  Progress on the East Building has reached level 3 as framing crews install wall panels and flooring.  This panelized method of installing wall panels is the quickest way of getting a building of this type constructed.  On average, framing crews can install an entire level […]

5
Dec

LIV Apartments – Construction Update – November

Construction, In Progress, LIV Apartments, Multi-family/Mixed Use, Project Update, Residential | Comments Off on LIV Apartments – Construction Update – November

Over the month of November at the LIV Apartments work crews progressed on all aspects of the project.  Painting crews have nearly completed their work on the exterior of the West Building and have shifted efforts to the South Building. At the South Building, masons work at ground level laying brick masonry along the south […]

20
Nov

LIV Apartments – Aerial Photos – Nov.

Aerial Photos, Construction, In Progress, LIV Apartments, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – Nov.

The progress thus far during the month November at the LIV Apartments job site shows progress on all avenues.  The North Building topped out last month so efforts have now shifted to waterproofing.  The white TPO roofing membrane has been added and work is now focused on waterproofing exterior openings such as windows and doors. […]

7
Nov

LIV Apartments – Construction Update – October

Construction, In Progress, LIV Apartments, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – October

There has been lots of recent progress on our LIV apartments project over the month of October located in Bellevue.   You can see the West building towering over the beginning stages of the East building.  This addition is the final component to this mix-use complex.  Phase 2 is moving along swiftly, with concrete and elevated […]

22
Oct

LIV Apartments – Aerial Photos – Oct.

Construction, Grouparchitect, In Progress, LIV Apartments, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – Oct.

October at the LIV Apartments was a busy month.  The most notable progress on site over the last month would probably be the framing of the North Building, which topped out at its highest point.  This signals the completion of the framing for phase 1 of the project.  The roof and waterproofing will soon follow […]

15
Oct

Phinney Ridge Prefab – Factory Visit

Construction, Custom home, In Progress, Prefab, Prefab/Modular, Residential | Comments Off on Phinney Ridge Prefab – Factory Visit

As progress at the Phinney Ridge Prefab project site continues since the demolition of the existing home, ongoing efforts on the home continues at the Method Homes factory in Ferndale, WA. Prefabrication of this home allows for a significantly reduced construction schedule, and also helps considerably for projects that are to be constructed in the […]

6
Oct

LIV Apartments – Construction Update – September

Construction, Grouparchitect, In Progress, LIV Apartments, Multi-family/Mixed Use, Phasing, Residential | Comments Off on LIV Apartments – Construction Update – September

September at the LIV Apartments was a busy month.  Trades worked on all aspects of the project from exterior cladding detailing and painting to interior gypsum board and work on unit interiors.  At the West Building, the gateway feature wall takes shape as the composite wood panels are installed and frame the western entrance to […]

3
Oct

Phinney Ridge Prefab – Demo

Construction, Custom home, In Progress, Prefab, Prefab/Modular, Residential | Comments Off on Phinney Ridge Prefab – Demo

The excavator is in the process of demolition of the existing home at the site of the new Phinney Ridge Prefab home project being careful for the neighboring homes and fences. Homes are no match for an excavator, also known as a track hoe.  The long reach of the boom and bucket is able to […]

1
Oct

TDX Renovation – September Update

Construction, In Progress, Multi-family/Mixed Use, Remodeling, Residential | Comments Off on TDX Renovation – September Update

The Theta Delta Chi renovation at the University of Washington continues as work on the roof, cladding, and window replacement progresses.  Additional structural members were required to take the load where the aging trusses have rotted and can no longer perform to their structural rating.  On top of the new roof structure, an almost completely […]

26
Sep

LIV Apartments – Aerial Photos – Sept

Aerial Photos, Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential, Uncategorized | Comments Off on LIV Apartments – Aerial Photos – Sept

The month of September brought progress across all areas of the LIV Apartments in Bellevue.  The South Building roof has been installed and progress continues on the window and exterior siding installation.  Interior plumbing and electrical rough in proceed in conjunction to maximize the potential of scheduling trades. Elsewhere, at the West Building, painters have […]

17
Sep

Phinney Ridge Prefab

Construction, Custom home, In Progress, Prefab, Prefab, Prefab/Modular, Residential | Comments Off on Phinney Ridge Prefab

The Phinney Ridge Prefab project will soon kick off as plans have been approved by the city and contracts signed for construction.  This new house will be built using pre-fab techniques utilizing the Grouparchitect designed Option Series offered in partnership with Method Homes. The existing home’s concrete block foundation was in poor condition and repair […]

10
Sep

LIV Apartments – West Gateway

Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – West Gateway

Original post 05/23/2014 As framing progresses at the LIV Apartments, a major design feature of the project is starting to take shape.  The “gateway” entrance off Bel-red Road is adorned with two story feature walls on both the North and West buildings, with the West building wall framing now ready to receive exterior sheathing. These walls […]