LIV Apartments – Aerial Photos – August

Aerial Photos, Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – August

Since the previous LIV Apartments aerial update last month, the progress on the three phase 1 buildings has continued, and construction broke ground on the East building.  The second phase of the project will include 99 residential units, several large amenity spaces, and two large roof decks. Elsewhere on site progress continues at a fever […]

2
Mar

LIV APARTMENTS – CONSTRUCTION UPDATE – LATE FEB. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – LATE FEB. 2014

The level 1 post tension slab poured and curing with materials to form the columns and next floor level staged for future use.  The previous slab on grade (parking level 1) is now the support for the ramped portion of level 1.  Next in the process will be to lay down sheathing, steel reinforcing, and […]

28
Feb

LIV APARTMENTS – CONSTRUCTION UPDATE – MID FEB. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – MID FEB. 2014

The LIV Apartments take the step to the next level as progress with concrete progresses.  Slab on grades have been poured and work now begins on new levels.  In order to hold the new levels a series of temporary scaffolds and cribbing will be used to support the weight of the concrete as it cures.  […]

28
Jan

LIV APARTMENTS – CONSTRUCTION UPDATE – LATE JAN. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – LATE JAN. 2014

The LIV Apartments are progressing nicely as this grade is prepared for concrete.  Prior to ground covering the various trades have been working to install main lines for plumbing and electrical as the opportunities to do sub grade work get substantially more difficult and expensive after concrete slab on grade is poured and cured. Before […]

15
Jan

LIV APARTMENTS – CONSTRUCTION UPDATE – EARLY JAN. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – EARLY JAN. 2014

After several months of excavation and ground work at the job site for the LIV Apartments works has transitioned to shoring and foundation work, plumbing & electrical, and the buildings are starting to grow from the ground.  The concrete work alone is scheduled to take ten months to complete and represents a large portion of […]