Construction is now underway on the renovation of Theta Delta Chi at the University of Washington. Work is beginning on the portico deck. Improvements to this portion of the building will include rot and damage repair, repairing of the columns & capitals, railing repair, a new waterproof deck, and improved access to the deck. Additional […]

25
Jul

LIV Apartments – Aerial Photos – July

Construction, In Progress, Multi-family/Mixed Use | Comments Off on LIV Apartments – Aerial Photos – July

The LIV Apartments progress continues into July as framing has started on the north building’s level 3 and framing has progressed to level 7 of the south building.  Panels and other materials have begun to be staged on the top post tensioned level of the north building as framing on level 4 will soon begin.Covered […]

7
Jul

LIV Apartments – Construction Update – June 2014

Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – June 2014

The month of June brought many advances to the LIV Apartments job site.  The most notable progress coming as the south building wood framing commenced.  With the previous experience of framing the west building the crews have picked up the pace and are moving very quickly with installing the panelized framing sections.Wood framing for the […]

26
Jun

LIV Apartments – Aerial Photos – June 2014

Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – June 2014

The latest aerial images of the LIV Apartments show the accelerated pace at which the wood framing is being constructed.  The west building framing is complete and work has begun on the south building as progress with framing starts to spread across the site as the structural concrete work is completed for the first phase […]

4
Jun

Leilani Gains LEED Certification

Green, Grouparchitect, LEED, Multi-family/Mixed Use, News, Residential | Comments Off on Leilani Gains LEED Certification

The Leilani Apartments, our most recently completed multi-family project, was just awarded LEED Certification.   From the start of the project the design team considered sustainability in all aspects of the project.  Through the selection of responsible materials, using local manufacturers and suppliers, utilizing water conservation measures, and many other improvements, the team aimed at designing […]

2
Jun

LIV Apartments – Construction Update – May 2014

Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – May 2014

During May, new heights were reached at the site of the ongoing LIV Apartments.  The most visual of the progress made in May is the west building.  Framing continued and reached level 5 of the 6 level building. Adjacent to the west building, the south building has also entered the framing stage.  Work has started […]

29
May

LIV Apartments – Aerial Views – May 2014

Construction, In Progress, Multi-family/Mixed Use, Residential, Uncategorized | Comments Off on LIV Apartments – Aerial Views – May 2014

The latest aerial images of the LIV Apartments have arrived and progress continues onward and upward. The post tensioned concrete floors of the south building have defined the buildings’ footprint, and the relationship of the South and West buildings can start to be seen. At the West building, Wood framing at is nearing completion and […]

13
May

LIV Apartments – Aerial Views – April 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Views – April 2014

We recently got our hands on these images and are excited to share another point of view of the ongoing LIV Apartments. Monthly photos of the jobsite are shot from an airplane from 2 angles to show construction progress from different points of view. The South and North buildings remain active with ongoing concrete formwork […]

2
May

LIV Apartments – Construction Update – Apr. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – Apr. 2014

Progress at the LIV Apartments has hit light speed in the month of April.  Wood framing has started to be erected at the west building while progress continues on concrete pours in other areas of the site. The east side of the site is still in the thick of concrete work as several levels are […]

11
Apr

LIV Apartments Site Tour

Construction, Multi-family/Mixed Use | Comments Off on LIV Apartments Site Tour

This Friday some of the office ventured out to the construction site of our largest ongoing multi-family residential project – the LIV Apartments. We were there to observe ongoing wood framing, progress with the post tensioned concrete pours, and to generally become familiar with the project by touring the site. LIV Apartments is situated half […]

31
Mar

LIV Apartments – Construction Update – Late Mar. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – Late Mar. 2014

Progress moved towards foundation walls nearing the end of March after pouring and curing slabs previously shown.  In the right of the picture is a cured slab and columns, and on the left is form work, reinforcing, and post tension cables ready for concrete to be poured.  progress will continue vertically as each level is poured […]

2
Mar

LIV APARTMENTS – CONSTRUCTION UPDATE – LATE FEB. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – LATE FEB. 2014

The level 1 post tension slab poured and curing with materials to form the columns and next floor level staged for future use.  The previous slab on grade (parking level 1) is now the support for the ramped portion of level 1.  Next in the process will be to lay down sheathing, steel reinforcing, and […]

28
Feb

LIV APARTMENTS – CONSTRUCTION UPDATE – MID FEB. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – MID FEB. 2014

The LIV Apartments take the step to the next level as progress with concrete progresses.  Slab on grades have been poured and work now begins on new levels.  In order to hold the new levels a series of temporary scaffolds and cribbing will be used to support the weight of the concrete as it cures.  […]

15
Jan

LIV APARTMENTS – CONSTRUCTION UPDATE – EARLY JAN. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – EARLY JAN. 2014

After several months of excavation and ground work at the job site for the LIV Apartments works has transitioned to shoring and foundation work, plumbing & electrical, and the buildings are starting to grow from the ground.  The concrete work alone is scheduled to take ten months to complete and represents a large portion of […]

27
Sep

LIV APARTMENTS – CONSTRUCTION UPDATE

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE

September marks the ground breaking for our newest apartment project located south of Microsoft’s Redmond campus.  Located at Bel-red Road and NE 22nd Place this 2 phase apt building will be home to 450 apartments in 4 distinct buildings partially built over a concrete podium for parking.  Over the months to come posts will detail […]

28
Mar

DJC: Fieldbrook Commons

Multi-family/Mixed Use | Comments Off on DJC: Fieldbrook Commons

Our rendering of the Fieldbrook Commons was featured in today’s Seattle Daily Journal of Commerce, http://www.djc.com/news/co/12051346.html

3
Jan

The Summit Apartments – DJC

Multi-family/Mixed Use | Comments Off on The Summit Apartments – DJC

The Summit Apartments by Grouparchitect and Triad Capital Partners in the Seattle Daily Journal of Commerce: http://www.djc.com/news/re/12048677.html

26
Nov

The Bellevue Apartments – DJC

Multi-family/Mixed Use | Comments Off on The Bellevue Apartments – DJC

The Bellevue apartments are highlighted in the Seattle Daily Journal of Commerce: http://www.djc.com/news/re/12047486.html

21
Nov

The Bellevue Apartments – SDJC

Multi-family/Mixed Use | Comments Off on The Bellevue Apartments – SDJC

The Bellevue apartments are featured in today’s Seattle Daily Journal of Commerce: http://www.djc.com/news/re/12047405.html and in the Seattle Times: http://seattletimes.com/html/businesstechnology/2019735421_goodmanbellevuexml.html

28
Aug

Bainbridge Island Residence

Multi-family/Mixed Use | Comments Off on Bainbridge Island Residence

The Bainbridge Island Residence, a custom prefabricated modular home, was featured in the Bainbridge Island Review.