Delano Apartments

completion, Delano Apartments, Grouparchitect, Mixed-Use, Redmond | Comments Off on Delano Apartments

The Delano Apartments are the 2012 recipient of the Outstanding Design Award in the City of Redmond’s Excellence in Design Awards. These apartments reside on a prominent corner site that is surrounded by fir trees within the Redmond Town Center.The exterior landscaping reflects a residential scale with respect to adjacent multifamily apartments as well as […]

16
Jan

LIV Apartments – Aerial Photos – Jan.

Aerial Photos, Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – Jan.

January has been a productive month at the LIV Apartments in Bellevue.  Progress on the East Building has reached level 5 as framing crews continue to install wall panels and flooring.  Seen in the photo above, crews are framing a lowered roof deck amenity space that will soon be covered with green roof, concrete pavers, […]

22
Dec

LIV Apartments – Aerial Photos – Dec.

Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – Dec.

December has been a busy month at the LIV Apartments.  Progress on the East Building has reached level 3 as framing crews install wall panels and flooring.  This panelized method of installing wall panels is the quickest way of getting a building of this type constructed.  On average, framing crews can install an entire level […]

20
Nov

LIV Apartments – Aerial Photos – Nov.

Aerial Photos, Construction, In Progress, LIV Apartments, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Aerial Photos – Nov.

The progress thus far during the month November at the LIV Apartments job site shows progress on all avenues.  The North Building topped out last month so efforts have now shifted to waterproofing.  The white TPO roofing membrane has been added and work is now focused on waterproofing exterior openings such as windows and doors. […]

7
Nov

LIV Apartments – Construction Update – October

Construction, In Progress, LIV Apartments, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – October

There has been lots of recent progress on our LIV apartments project over the month of October located in Bellevue.   You can see the West building towering over the beginning stages of the East building.  This addition is the final component to this mix-use complex.  Phase 2 is moving along swiftly, with concrete and elevated […]

6
Oct

LIV Apartments – Construction Update – September

Construction, Grouparchitect, In Progress, LIV Apartments, Multi-family/Mixed Use, Phasing, Residential | Comments Off on LIV Apartments – Construction Update – September

September at the LIV Apartments was a busy month.  Trades worked on all aspects of the project from exterior cladding detailing and painting to interior gypsum board and work on unit interiors.  At the West Building, the gateway feature wall takes shape as the composite wood panels are installed and frame the western entrance to […]

10
Sep

LIV Apartments – West Gateway

Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – West Gateway

Original post 05/23/2014 As framing progresses at the LIV Apartments, a major design feature of the project is starting to take shape.  The “gateway” entrance off Bel-red Road is adorned with two story feature walls on both the North and West buildings, with the West building wall framing now ready to receive exterior sheathing. These walls […]

5
Sep

LIV Apartments – Construction Update – August

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – August

The month of August brought advances to several areas of construction at the LIV Apartments in Bellevue.  Framing across the site continues upward as crews race to beat the oncoming fall weather. The North Building, the largest of the buildings, framing reached to level five of eight.  Construction speed was increased on the project by […]

2
Jun

LIV Apartments – Construction Update – May 2014

Construction, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – May 2014

During May, new heights were reached at the site of the ongoing LIV Apartments.  The most visual of the progress made in May is the west building.  Framing continued and reached level 5 of the 6 level building. Adjacent to the west building, the south building has also entered the framing stage.  Work has started […]

2
May

LIV Apartments – Construction Update – Apr. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV Apartments – Construction Update – Apr. 2014

Progress at the LIV Apartments has hit light speed in the month of April.  Wood framing has started to be erected at the west building while progress continues on concrete pours in other areas of the site. The east side of the site is still in the thick of concrete work as several levels are […]

2
Mar

LIV APARTMENTS – CONSTRUCTION UPDATE – LATE FEB. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – LATE FEB. 2014

The level 1 post tension slab poured and curing with materials to form the columns and next floor level staged for future use.  The previous slab on grade (parking level 1) is now the support for the ramped portion of level 1.  Next in the process will be to lay down sheathing, steel reinforcing, and […]

28
Feb

LIV APARTMENTS – CONSTRUCTION UPDATE – MID FEB. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – MID FEB. 2014

The LIV Apartments take the step to the next level as progress with concrete progresses.  Slab on grades have been poured and work now begins on new levels.  In order to hold the new levels a series of temporary scaffolds and cribbing will be used to support the weight of the concrete as it cures.  […]

28
Jan

LIV APARTMENTS – CONSTRUCTION UPDATE – LATE JAN. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – LATE JAN. 2014

The LIV Apartments are progressing nicely as this grade is prepared for concrete.  Prior to ground covering the various trades have been working to install main lines for plumbing and electrical as the opportunities to do sub grade work get substantially more difficult and expensive after concrete slab on grade is poured and cured. Before […]

15
Jan

LIV APARTMENTS – CONSTRUCTION UPDATE – EARLY JAN. 2014

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE – EARLY JAN. 2014

After several months of excavation and ground work at the job site for the LIV Apartments works has transitioned to shoring and foundation work, plumbing & electrical, and the buildings are starting to grow from the ground.  The concrete work alone is scheduled to take ten months to complete and represents a large portion of […]

27
Sep

LIV APARTMENTS – CONSTRUCTION UPDATE

Construction, Grouparchitect, In Progress, Multi-family/Mixed Use, Residential | Comments Off on LIV APARTMENTS – CONSTRUCTION UPDATE

September marks the ground breaking for our newest apartment project located south of Microsoft’s Redmond campus.  Located at Bel-red Road and NE 22nd Place this 2 phase apt building will be home to 450 apartments in 4 distinct buildings partially built over a concrete podium for parking.  Over the months to come posts will detail […]