Category 'Apartment'

13
Jun

The Mercantile – Construction Progress – June 2016

Apartment, Bothell, construction, framing, Multifamily, progress, The Mercantile | Comments Off on The Mercantile – Construction Progress – June 2016

Level 3’s PT slab was poured earlier this month, allowing the wood framing construction to begin. There is a 2 story elevation change from the west side of the property, off of 102nd Ave NE, to the east side of the property.  The topography meets the third floor on the east end of the building, […]

18
Apr

The Mercantile – Construction Progress – April 2016

Apartment, Bothell, construction, Multifamily, progress, pt slab, slab on grade, The Mercantile | Comments Off on The Mercantile – Construction Progress – April 2016

The slab on grade is complete on the Mercantile site, located in Bothell.  The concrete columns are erected at the ground level.  Soon after, the level 2 deck was prepped for a concrete pour.The forms were constructed and lined with reinforced bars and ties, as illustrated in the image below.  The formwork for the concrete […]

22
Mar

The Mercantile – Construction Progress – March 2016

Apartment, Bothell, Breaking ground, construction, foundation, Multifamily, progress, Residential, The Merc, The Mercantile | Comments Off on The Mercantile – Construction Progress – March 2016

Over the past couple weeks the construction team has been pouring the remaining columns of the subgrade garage. The foundation and footings are complete and the second level PT slab will be poured in the next couple weeks.Keep updated with the Mercantile project by clicking here.

25
Jan

The Mercantile – Construction Progress – January 2016

Apartment, Bothell, construction, Demolition, excavation, foundation, grading, Multifamily, progress, The Mercantile | Comments Off on The Mercantile – Construction Progress – January 2016

The images illustrate the progress made over these past couple of weeks. The excavation process is complete on The Mercantile, a multifamily project located in Bothell. The construction teams have poured the footings and have erected the temporary shoring walls around the perimeter of the building. They are beginning to construct the subgrade garage walls.The […]

28
Dec

The Mercantile – Construction Progress – December 2015

Apartment, Bothell, construction, Demolition, grading, Multifamily, progress, The Mercantile | Comments Off on The Mercantile – Construction Progress – December 2015

The Mercantile located in Bothell, WA has completed demolition of the existing commercial building. The historic unreinforced masonry façade has been preserved along 102nd ave and the rest of the site has been cleared and graded.We are excited to see the next steps for The Mercantile, keep track of the construction progress by clicking here.