LIV Apartments – Construction Update – June 2014
July 7, 2014
The month of June brought many advances to the LIV Apartments job site. The most notable progress coming as the south building wood framing commenced. With the previous experience of framing the west building the crews have picked up the pace and are moving very quickly with installing the panelized framing sections.Wood framing for the south building commenced, and reached to level 6 before the end of the month. As progress continues vertically, other building elements are added such as...