LIV Apartments – Construction update January
2015 arrives at the job site of the LIV Apartments in Bellevue as crews work at a fevered pace on both the exterior and interior of phase one, and on the framing of the phase 2 East Building. At breaks in the weather painting crews are able to paint the cement board panel siding that the siding subcontractor installed. Painting progress on the West and South Buildings is nearly complete so the focus has shifted towards the north building. The podium level,...