Laurelhurst Residence – Construction Update

The Laurelhurst wine room has quickly progressed into the construction in the recent weeks since the client approved the design and engaged their contractor. An interesting challenge with this renovation, as in many others, is the owner will maintain occupancy in the house while the work it being done.  Special care is taken to reduce airborne dust, dirt, and other debris from entering the rest of the home.  This construction door separates the work area from the rest of the house...

Clyde Hill – Construction Update – May

May was a great month at the Clyde Hill Residence job site.  The contractors have completed the installation of exterior wood siding, cement board panels, and trim giving the exterior of the home a completely new design aesthetic.  The clear finished wood siding emphasizes the horizontality of the home and provides a material connection to the landscape of the lot. The full impact of the new redesigned entryway is starting to be felt with the wood siding balancing the large floor...

Blower Door Testing

With the implementation of the 2012 Washington State Energy Code the requirements for air testing residential projects have changed to become more restrictive.  All new residences and additions in the state now require a blower door test to measure air leakage through the building envelope.  The test requires that air changes be less than 5 per hour, hopefully pushing towards tighter building envelopes and less energy consumption. Blower door testing may seem mundane and ordinary, but when the Godfather of Soul...

Clyde Hill – Construction Update – Late Apr. 2014

Progress on the Clyde Hill Residence progressed into late April with a push on exterior elements including finishing the windows and doors, and completing the shingled roof.  The exterior of the home has also been wrapped with building felt in preparation for cement board and cedar strip siding. The redesigned entry now has windows and a door and is ready to be trimmed out and have siding attached. At the back deck and patio the waterproofing has been completed, and the new...

Laurelhurst Residence – Wine Room Sketches

Earlier in April, we were excited for the opportunity to work, once again, with great clients on a small wine room renovation to their home.  The previously completed new construction left some room for renovation as the clients grew into the home and developed some ideas of how to improve the home to suit their needs better.  Architect Emily McNichols generated sketches to start a conversation with these clients about how a wine room could fit into the lower level of their...

Clyde Hill – Construction Update – Mid Apr. 2014

The Clyde Hill Residence progresses into April with more work being to the exterior.  The covered porch at the rear of the house has been fully framed and prepared for the future finishes.  New foundation pads have been cast to support the weight of the porch and roof above, and new membrane is being installed at the living room opening and floor. Bulk was added to anchor the home above the hillside and to give weight to the non enclosed building...

Clyde Hill – Construction Update – Mar. 2014

This March has been a busy month for the Clyde Hill Residence as the entryway and entry roof have completed framing, the exterior is stripped of existing cladding, and the interior framing is pushing towards completion.  March also saw the installation of most the windows and exterior doors.  Once this installation is complete work will be at a rapid pace on the interior of the building as construction moves towards drywall, fixture installation, painting & finishes, and move in. These views...

Clyde Hill – Construction Update – Feb. 2014

As progress on the Clyde Hill Residence moves forward this post will document progress made during the month of February. As this project was taken over mid renovation our work has been to tweak the design our clients’ desires.  These tweaks are enlarging rooms & windows, removing windows & exterior cladding, adding a new roof over the main entry, and more will come in posts to come. View up the hill toward the living room and deck side of the home...

Clyde Hill Remodel – Week 1

The Clyde Hill Remodel has begun in earnest. Per our Client’s desire to be moved into the home as soon as possible and given that the project was already under construction, we have been working within the existing building’s envelope as much as possible. Our initial concept sketch for the main floor focuses on preserving the west-facing view windows and collecting the great room and kitchen areas around them. The master bedroom and bathroom were also kept on this floor...

Clyde Hill Remodel Begins

Our newest custom residential project began today in Clyde Hill. Our clients had been looking for several months for a site for a new custom home in the Clyde Hill / Medina / Yarrow Point neighborhoods and finally found their spot. The site was actually a speculative build by local custom home builder Lochwood-Lozier. Project construction will be placed temporarily on hold while we begin integrating our client’s program and vision into the existing structure. Check back in the coming...