Clyde Hill Remodel Completion

This project was a custom remodel to an existing home in Clyde Hill.  The original home was a traditional brick house with a similar shingled, pitched roof.  The home’s interior and exterior was completely revamped. A new courtyard and water feature adorn the remodeled vaulted entry and window wall.  The large cantilevering entrance provides coverage […]

4
Aug

Clyde Hill – Construction Update – July

Construction, Custom home, Finishes, In Progress, Kitchens, Master Bedroom, Materials, Products, Remodeling, Residential | Comments Off on Clyde Hill – Construction Update – July

The efforts for completing the Clyde Hill Residence renovation have shifted to the interior during the month of July as painting, staining, and finishing details are completed. The light finish of the cabinetry, along with the white paint and abundance of windows throughout the house keeps the home bright and cheerful during all hours of the […]

27
Jun

Clyde Hill – Construction Update – June

Construction, In Progress, Materials, Remodeling, Residential | Comments Off on Clyde Hill – Construction Update – June

The Clyde Hill Residence finishes and interiors are starting to define the large open living, dining, and kitchen spaces as casework and custom cabinetry have been installed.  Additionally bamboo plank flooring has been installed throughout the main level of the house and has been covered to protect it during the remainder of construction. The fireplace […]

2
Jun

Clyde Hill – Construction Update – May

Construction, In Progress, Remodeling, Residential | Comments Off on Clyde Hill – Construction Update – May

May was a great month at the Clyde Hill Residence job site.  The contractors have completed the installation of exterior wood siding, cement board panels, and trim giving the exterior of the home a completely new design aesthetic.  The clear finished wood siding emphasizes the horizontality of the home and provides a material connection to […]

1
May

Clyde Hill – Construction Update – Late Apr. 2014

Custom home, Grouparchitect, Remodeling, Residential | Comments Off on Clyde Hill – Construction Update – Late Apr. 2014

Progress on the Clyde Hill Residence progressed into late April with a push on exterior elements including finishing the windows and doors, and completing the shingled roof.  The exterior of the home has also been wrapped with building felt in preparation for cement board and cedar strip siding. The redesigned entry now has windows and […]

18
Apr

Clyde Hill – Construction Update – Mid Apr. 2014

Construction, Grouparchitect, In Progress, Remodeling, Residential | Comments Off on Clyde Hill – Construction Update – Mid Apr. 2014

The Clyde Hill Residence progresses into April with more work being to the exterior.  The covered porch at the rear of the house has been fully framed and prepared for the future finishes.  New foundation pads have been cast to support the weight of the porch and roof above, and new membrane is being installed […]

31
Mar

Clyde Hill – Construction Update – Mar. 2014

Construction, Grouparchitect, In Progress, Remodeling, Remodeling, Residential | Comments Off on Clyde Hill – Construction Update – Mar. 2014

This March has been a busy month for the Clyde Hill Residence as the entryway and entry roof have completed framing, the exterior is stripped of existing cladding, and the interior framing is pushing towards completion.  March also saw the installation of most the windows and exterior doors.  Once this installation is complete work will […]

28
Feb

Clyde Hill – Construction Update – Feb. 2014

Construction, Grouparchitect, In Progress, News, Remodeling, Residential | Comments Off on Clyde Hill – Construction Update – Feb. 2014

As progress on the Clyde Hill Residence moves forward this post will document progress made during the month of February. As this project was taken over mid renovation our work has been to tweak the design our clients’ desires.  These tweaks are enlarging rooms & windows, removing windows & exterior cladding, adding a new roof […]

17
Jan

Clyde Hill Remodel – Week 1

In Progress, Remodeling | Comments Off on Clyde Hill Remodel – Week 1

The Clyde Hill Remodel has begun in earnest. Per our Client’s desire to be moved into the home as soon as possible and given that the project was already under construction, we have been working within the existing building’s envelope as much as possible. Our initial concept sketch for the main floor focuses on preserving […]

10
Jan

Clyde Hill Remodel Begins

In Progress, Remodeling | Comments Off on Clyde Hill Remodel Begins

Our newest custom residential project began today in Clyde Hill. Our clients had been looking for several months for a site for a new custom home in the Clyde Hill / Medina / Yarrow Point neighborhoods and finally found their spot. The site was actually a speculative build by local custom home builder Lochwood-Lozier. Project […]