LIV Apartments – Construction Update – November
Over the month of November at the LIV Apartments work crews progressed on all aspects of the project. Painting crews have nearly completed their work on the exterior of the West Building and have shifted efforts to the South Building. At the South Building, masons work at ground level laying brick masonry along the south façade, cladding crews install the weather barrier and cement board siding, and the painters follow behind. Wall panel installation at the east building continues, and current progress...