LIV Apartment – Aerial Photos – April

We have made a lot of progress at the LIV Apartment construction site. The exterior of the East Building is near completion. The East Building has the windows installed and is currently being wrapped with a weather protective membrane. The construction team will begin installing the concrete pavers and landscape to the roof decks, which will be complete with a green roof, dog run, planters, and trees. The South Building’s lower deck is taking form with cast in place benches and...

Phinney Ridge Prefab – On Site Construction

The Phinney Ridge pre-fab home has seen a lot of changes over the past 2 months. Since our last update the rest of the fiber cement boards were placed on the front façade of the home. Construction of the front porch has begun, the framing, roof, and railings are in place. The driveway and retaining walls were cast and poured. When the modules were set in place, a lot of the interior work was already completed at the factory. Prefabrication allows the...

Phinney Ridge Modular Construction Time Lapse

The prefab collaboration with Method homes was pieced together in the Phinney Ridge neighborhood of Seattle. This Option series house was custom built over the last few months and it was erected in the month of January 2015. We have documented the process of this prefabricated home in our previous blog posts. The time lapse video illustrates the quick process of setting the modular in place. The neighborhood was able to witness a two story home being built in one...

LIV Apartments – Aerial Photos – March

Construction has been moving along during the month of March, the exterior framing of the East Building has been completed.  All the windows on the westerly buildings have been installed and the construction team is continuing to wrap the building with the weather protective membrane and continue installation of the building’s cladding systems.Due to the great weather exterior work such as painting, cladding, and site work have been accelerated accordingly. The landscaping and construction team has been busy applying finishes...

LIV Apartments – Construction Update Mid March 2015

The exterior shells of the North, South, East and West buildings were completed.  As you can see in the image above, the North Building’s building wrap is being applied against the sheathing.  It will soon look similar to the South Building, shown on the right, with the exterior finishes installed and painted. The corten steel planters have been placed in the lower plaza deck of the North Building with seat wall benches in cast-in-place concrete. These benches will receive a wood...

LIV Apartments – AERIAL PHOTOS – Feb.

Construction at the LIV Apartments in Bellevue has made substantial progress in the recent month.  The East building has reached level 6 of framing and flooring including roof trusses.  The framing of the lower roof deck amenity space on the 5th level is complete and the green roof, concrete pavers, dog run, planters, and trees will be installed next. The large crane previously located in the center of the plaza was removed as the North, South, and West buildings are nearing...

LIV Apartments near Microsoft on Bel-Red Road in between Bellevue and Redmond. 450 Unit upscale apartment development.

LIV Apartments – Construction Update mid Jan 2015

On a recent office site visit to the ongoing LIV Apartments in Bellevue our team was able to observe all of the various stages of construction the project is currently in. This project utilizes phasing as strategy to minimize construction time by distributing the construction over multiple buildings so that the various trades can work without interruption.  For instance, at the second phase, also known as the East Building, framing has only recently started as this phase was delayed so that...

LIV Apartments near Microsoft on Bel-Red Road in between Bellevue and Redmond. 450 Unit upscale apartment development.

LIV Apartments – Aerial Photos – Jan.

January has been a productive month at the LIV Apartments in Bellevue.  Progress on the East Building has reached level 5 as framing crews continue to install wall panels and flooring.  Seen in the photo above, crews are framing a lowered roof deck amenity space that will soon be covered with green roof, concrete pavers, a dog run, planters, and trees.  This East Building will have one more level of apartments and amenity spaces before the roof trusses cap the...

Capitol Hill Apartments – Construction Update – January

Our Capitol Hill Apartment project has been progressing through the wet season.  The construction team has been busy with the foundation forms now that shoring has been installed.  The reinforcing rebar can be seen protruding from the completed concrete footings.  The columns are due to be poured later this week, followed by the perimeter foundation walls. The column forms are assembled including rebar and awaiting the future concrete pour. Stay tuned for updates on our Capitol Hill Apartment project!...

LIV Apartments near Microsoft on Bel-Red Road in between Bellevue and Redmond. 450 Unit upscale apartment development.

LIV Apartments – Construction update January

2015 arrives at the job site of the LIV Apartments in Bellevue as crews work at a fevered pace on both the exterior and interior of phase one, and on the framing of the phase 2 East Building. At breaks in the weather painting crews are able to paint the cement board panel siding that the siding subcontractor installed.  Painting progress on the West and South Buildings is nearly complete so the focus has shifted towards the north building. The podium level,...